the past three weeks have been very productive at the site. in that time we dug, formed, and poured 20 yds of footings( all by hand). two of the hall's walls are blocked to the finished height. we formed and poured two of the four pilasters, and today we poured an finished the concrete floor. during the three weeks it's been either uber hot or it's been pouring down rain, but the work has continued. the work has been difficult but spirits are high, life is good in kosrae